Bunker Update

The bunker project is moving along nicely. We estimate another 3 weeks until all bunkers are complete and ready for play. Each bunker has been shelled out, new drainage system put in place and than a layer of porous asphalt has been put down (see photo). The asphalt allows water to pass through to the drainage system without allowing soil to contaminate the bunker. After that process is completed new sand is filled and than compacted down with machinery. All bunkers will remain ground under repair until the process is finished. We look forward to providing the best playing experience with new bunkers this year!